| La Laguna | 4–8 | 12–24 · Conjunto Histórico, plots that need a heritage study | High |
|---|
| Los Realejos | 6–12 | 12–18 · A brand-new plan: fewer grey areas, but first-year questions | Medium |
|---|
| Santa Úrsula | 9–18 | 18–24 · Small council: one architect can make it fast, or freeze it | Low |
|---|
| El Sauzal | 9–18 | 18–24 · Small council: one architect can make it fast, or freeze it | Low |
|---|
| Tegueste | 9–18 | 18–24 · Airport-easement zones | Low |
|---|
| Icod de los Vinos | 12–24 | 18–30 · Rural land that needs Cabildo reports | Low |
|---|
| San Juan de la Rambla | 12–24 | 18–30 · Protected and rural land | Low |
|---|
| Los Silos | 12–24 | 24–36 · Plots in or near the Teno rural park | Low |
|---|
| La Guancha | 12–24 | 18–30 · Protected and rural land | Low |
|---|
| Tacoronte | 12–24 | 18–30 · Airport-easement zones | Medium-low |
|---|
| Puerto de la Cruz | 12–24 | 18–30 · Heritage buildings and an old general plan | Medium-low |
|---|
| La Victoria | 12–24 | 18–30 · Small council: one architect can make it fast, or freeze it | Low |
|---|
| La Matanza | 12–24 | Coastal strip: effectively blocked until the Cabildo plan exists | Low |
|---|
| La Orotava | 12–24 | 24–36+ · Historic centre, and areas the new supplementary plan changes. Its approval could bring typical cases down to 9–15 months. | Medium-low |
|---|
| El Tanque | 12–30 | 24–36 · Protected and rural land | Low |
|---|
| Buenavista del Norte | 18–30 | 24–36+ · Teno rural park, with a binding report that has no deadline | Low |
|---|
| Garachico | 18–30 · outside the historic centre | 36–60 · inside the historic centre | Medium |
|---|